CM25 - Order start

$
0
0

We use CM25 for leveling our machine capacity. We got a scenario where no new production orders should start in middle of the day. For example, shift start 06:00:00 and ends 14:00:00.  If a production order 1 will finished today at 11:30:00 then next order should not start today. The new order should be dispatched to next day.

 

Is there a way we can get this using automatic dispatch function ?

 