Hi,
The following example is as same as my requirement. But Planned Order type VP doesn't reduce its qty in next MRP Run as underlined in the e.g.,
Strategy : 50 , Ind / Coll : 2.
Consumption Indicator : 2 in OMPO.
Example: If a planned independent requirement of 100 pieces exists and you receive a sales order for 40
pieces which consumes the planned independent requirements then the sales order for 40 pieces remains
in the individual customer planning segment and a planned independent requirement for 60 pieces remains
in the net requirements segment. As soon as the product is planned again in the next MRP run, the system
creates a planned order for 40 pieces in the individual customer planning segment which you can convert into a
production order. At the same time, the system reduces the existing planned order of type VP from 100 pieces
to 60 pieces.
Thanks With Regards,
Dinesh V.