Problem: Release strategy is getting triggered when price or quantity is decreased at version 0.
PO is created referencing a PR. Version 0 is marked complete due to setting in config.
Release strategy characteristic include PO type and version number. PO is not approved on creation.
1) Quantity decreased by 1. Version 1 created and Release strategy triggered. PO went for approval.Now PO is in approved status.
2) Decrease price on PO item. Version 2 got created but release strategy was not triggered.
3) Increase price on PO item. Version 3 got created and Release strategy was triggered.
4) Decrease price on PO item. Version 4 got created but release strategy was not triggered.
5) Increase price on PO item. Version 5 got created and Release strategy was triggered.
So on version 1 Release strategy triggered when we decreased the price where else it only triggers release strategy on increase of value of PO on higher versions.
Is this a standard behavior that Release strategy would be triggered for price/quantity increase or decrease if PO is not in approved status?
Thank You,
Pavan