Monthly planning and MRP run

$
0
0

Hi Gurus

 

Hope that all are doing good.

 

My client business is on basis of MTS scenario.

He is getting monthly fix plan for production from customer, this fixed plan is closes every monthend.

It means If there is any open PR or PrdOrd it is NOT CARRY FORWARDED into next month.

 

I want to run MRP for current month only, irrelevant to the last month plan and open requirements.

 

kindly help me to drop open requirement from last month during the MRP run.

 

I have done some experiment using Firming and Roll forward days options. but I am not much clear about this.

 

Please help me on this, correct answer will be rewarded into points.

Your help will be valuable for me.

 

Thanks in advance

AKSHAY

SAP PP