Hi All,
I have projects which need to be closed. I am aware of all the pre-requisites for closing the project.
We are have only WBS elements in our project and we have to close projects which is unclosed from 15 years. the issue is till 2005 settlement rule was created and settlement is done to PSG. after 2006 for other projects starting from 2007 Settlement rule is not maintained.
What are the steps to be followed to close all these projects if
1. There are commitments on the wbs
2. If there is actual cost on wbs
3 if project cost is on wbs
4. If un utilised budget is still remaining
5 If wbs elements are already settled.( How to find the wbs elements which are already settled)
We are using customer projects which is using sales order and wbs is released and assigned to the sales order line items and after budget approval procurement cycle is done.
I need your suggestions to approach this issue.
regards,
GVK