Experts,
I have a very strange requirement. I have a FG and BOM. when I run MRP, I need system to create dep. requirements for bom components, but system should not create planned order for FG. I understand this looks stupid, but want to see if there is any way to achieve this?
The only way I thought was to set SPK 60 for FG , but that is not working too...
Note: I dont want to use SPK 50 because I need to sell this FG. The reason for this peculiar requirement is the execution is done in an external system and the stock is uploaded to SAP on FG as we ship through SAP and we don't care about consumption of components or labor but we need to procure the components through SAP and thats the reason we need BOM explosion.