Dear All,
I have created standard cost estimate by using CK11N and saved it successfully. While executing CK24 the system is showing message "Of 0 materials, 0 cost estimates were updated successfully".
I can see the std cost estimate by using CK13N it means that there is no problem with it.
Current period is 03 in system and in ck11n i have given the below data:
Costing from date:05/06/2015
Costing date to:31.12.9999
Qty structure date:05/06/2015
Valuation date:05/06/2015
I know there are tons of threads for this by not able to resolve it by following them.
Please guide
Regards