Hello,
For Indirect Activity Allocation there are two types
planned indirect activity allocation & Actual indirect activity allocation
For creation of Actual indirect activity allocation cycle
1. FB50 postings
2. Enter sender activities in KB51N
3. Enter statistical key figures KB31N
4. Cycle creation (KSC1)
5. Run cycle (KSC5)
Note in KSC1 options available are :
Receiver tracking factor :variable proportions
variable proportion type : 5 Actual statistical key figures (which we give in KB31N Actuals)
For Actual Indirect activity allocation
1. KP06
2. KP26
3. KSPI
4. Cycle creation (KSC7)
5. Run cycle (KSCB)
For creating cycle in KSC7 ,there is an option for variable proportion type : 6 planned statistical key figures
My question is where do we define this planned statistical key figure
Thanks & Regards,
Janaki panchagnula.