HI, Expert:

     I work in ECS.

     The SRM standard function can support the budget checking based on WBS or internal order. Can I do the budget checking based on cost center ?

The ECC funds management is actived. And the match is done between cost center and funds center. I create the PO withe this cost center , there is the budget checking message. But I create the PO in SRM and check the budget ,then no any message about the budget .

     How I can active the budget checking based on CC?

    BR

     Alex