Dear SAP Gurus,
I have created a process order (backward scheduling) and the scheduled start date is 29.07.2015 with Finish date as 31.08.2015. Lead time is not quantity dependent.
Now I carried out Confirmation for Phases 20 and 40. Still Phases 60,80 and 100 need to be confirmed. After Confirmation completion of phases 20 and 40, when I checked the process order the Scheduled start and finish date on order header was remaining the same. Even in Operation Overview tab ,the latest start/Finish date for the phases 20 and 40 was remaining the same.
Now when I did some changes to Process Order Qty or calling scheduling again(without any change to qty), on both cases the scheduled start date changes in the order header and it now displays the date of next pending Operation (Oper 50) start date.
My query is :
1. Why the Basic/scheduled start date in PO header page and latest start/Finish date in Operation tab (for confirmed phases) is not getting changed as soon as confirmation is saved ?
2. Why the Basic/scheduled start date in PO header page gets changed (depending on start date of pending next operation) when a Qty change is done/Scheduling called again - Is this a SAP standard process order phenomena?
I have attached screen shot for reference.
Thanks in advance.