Hi PP experts,
The quantity of component A5X01614181 was changed from 2pc to 4pc in BOM, and the valid from date is 13.07.2015.
And the PrdOrd quantity is 1 for FERT A5E35208899. Why the reqd.qty is 4- during 08.07.2015~10.07.2015? I think it should be 2- because valid from date is 13.07.2015.
Could you please give me some advises, do I need to check other date? Thank you.
Regards,
Steve