Dear Friends,
We have a go live this saturday for MM-Purchasing module. We did not get any down time. i am not clear about the sequence of steps to be performed in ECC and BW. In quality system i performed filling up set table and loading data to BW which is taking approximately 7 hours.
My data flow is direct load to Info cube using 2lis_02_ITM and SCL datasources.
My plan is to perform below steps. correct me if iam wrong. We do not have down time.
Step 1: Move ECC TR to ECC- PRD system
Step 2: Replicate datasources in BW -PRD
Step 3: Move BW TRs to BW PRD system
Step 4: Delete set up table
Step 5 : Fill set up table (
Step 6: Run infopackage Init delta with data transfer.
Step 7: Delta load via process chain on daily basis.
Q1. After deleting set up table do i have to fill set up table or should i run infopackage init without data transfer and fill set up table.? here also am confused about which Init delta i need to use to load full load.
Q2. do i need to load master data first? if yes. Should i follow the same steps for master data load?
Q3. how do u know that i have pulled correct data without missing any records posted during this activity.
Q4. should i use only delta infopackage in my process chain?
Please guide me with your valuable input.
Thanks
Vijay