Dear Experts,
reg -Cost element assignment in Material cost component under Cost component structure
As per my understanding we only assign - GBB- VBR(CONSUMPTION THROUGH ORDER) and GBB-VBO (CONSUMPTION THROUGH SUB CON ORDER) in our cost component structure as a Material cost.
but in my project, GBB-AUF(GR against order) cost element also assigned in cost component under other material cost component.
My question is
1) Why GBB-AUF cost element assigned in cost component structure as a other material cost?. As per my understanding this cost element not required in standard price release or cost component structure.
2)Due to Actual costing / material ledger , GBB-AUF assignment is required in Material cost component under Cost component structure?.
regards
Mohit